Recycled Aluminum Smelting and Ingot Casting Plant

Recycled aluminum smelting and ingot casting plant with 174 t/day reference capacity, twin-chamber furnace, alloy furnaces, casting, palletizing, dross recovery and dust collection.

Twin chamber recycled aluminum melting furnace
Twin-chamber melting furnace from the supplied recycled-aluminum proposal

This dedicated recycled-aluminum plant follows the supplied process: scrap sorting and pretreatment, melting, alloy adjustment, degassing and refining, ingot casting, robotic or manual palletizing, aluminum-dross recovery and compliant flue-gas collection.

Capacity and Technical Parameters

Preliminary engineering selection range: The standard line below follows the supplied 174 t/day, 288-day/year example. Compact and expanded ranges are planning bands derived from the same modular equipment route; final yield and fuel use require scrap analysis and heat-balance confirmation. Final guaranteed values require confirmed feed/product data, utility quality, operating schedule, site conditions and acceptance protocol.

Parameter Compact line Supplied reference line Expanded / parallel line
Finished alloy-ingot output 30–80 t/day 174 t/day 200–350+ t/day
Annual operating basis Project-specific 288 days/year; about 50,112 t/year Project-specific parallel operation
Main melting furnace 30–60 t twin-chamber furnace 1 × 100 t twin-chamber furnace 2 × 100 t or equivalent parallel furnaces
Alloy / holding furnaces 1–2 × 20–35 t 2 × 35 t single-chamber alloy furnaces Multiple 35–60 t alloy / holding furnaces
Ingot casting 1–2 lines 4 × 20 m spray-type ingot casting machines 4–8 lines sized to casting cycle
Dross / aluminum-ash recovery 1 × 3–5 t rotary furnace 2 × 8 t rotary furnaces + Φ1900 cold-ash buckets Parallel hot-dross and cold-ash treatment trains
Dust collection Sized by hood and gas volume 355 kW pulse-bag dust collector in supplied example Multiple zones / duty trains based on emissions study

Process Configuration Flow

Scrap sorting

Pretreatment

Twin-chamber melting

Alloy adjustment & refining

Ingot casting

Palletizing & storage

Dross recovery & dust collection

Factory Route Reference Images

Main Equipment and Systems

  • Scrap receiving, sorting and non-metal removal
  • Twin-chamber scrap-melting furnace
  • Single-chamber alloy / holding furnaces
  • Degassing, refining, filtration and launders
  • Spray-cooled ingot casting machines
  • Robotic or manual ingot palletizing
  • Rotary furnace and cold-ash screening bucket
  • Fume hoods, ducting and pulse-bag dust collection

Customer Engineering Inputs

Provide scrap categories and contamination limits, monthly chemistry and moisture data, target alloy grades, daily and annual output, fuel and electrical data, cooling-water conditions, emissions limits, building/plot plan, local codes and required automation.

Utilities and Environmental Interfaces

Engineering covers scrap contamination control, enclosed fume capture, bag filtration, aluminum-dross handling, hot-material safety, cooling-water circulation, noise, fire protection, residue outlets and occupational exposure. Any salt-flux or hazardous-residue route must be confirmed separately.

Frequently Asked Questions

Is this primary aluminum electrolysis?

No. This page is based on the supplied recycled-aluminum scrap melting and alloy-ingot casting proposal.

What is the supplied reference capacity?

The source proposal uses 174 tonnes of aluminum-alloy ingots per day and 288 operating days per year.

What is the main furnace configuration?

The supplied example uses one 100-ton twin-chamber melting furnace and two 35-ton single-chamber alloy furnaces.

How is ingot casting configured?

The supplied example lists four 20-meter spray-type ingot casting machines and two robotic ingot-palletizing systems.

How is aluminum dross treated?

The supplied example uses two 8-ton rotary furnaces and two Φ1900 screening-type cold-ash buckets to recover residual metal.

Are compact and expanded outputs guaranteed?

No. Only the 174 t/day example comes directly from the supplied proposal; other bands are preliminary modular planning ranges.

Request a Project Evaluation

Process, equipment images and the 174 t/day reference configuration are taken from the aluminum document supplied by the client. Company-logo pages and visibly branded images were not used.